HARGA SATUAN TERTINGGI |
||
|
URAIAN KEGIATAN |
SATUAN |
HARGA |
|
I. PEKERJAAN GALIAN TANAH |
||
|
A. Dengan Tenaga Manusia |
||
|
1. a. Galian tanah sedalam 1 m |
M3 |
4.100 |
|
b. Galian tanah sedalam 2 m |
M3 |
5.250 |
|
c. Galian tanah sedalam 3 m |
M3 |
6.000 |
|
2. Galian tanah berbatu |
M3 |
9.250 |
|
3. Galian tanah keras |
M3 |
5.500 |
|
4. Galian tanah berlumpur |
M3 |
8.200 |
|
B. Dengan Alat Berat |
||
|
1. Galian tanah biasa |
M3 |
2.750 |
|
2. Galian tanah berbatu |
M3 |
4.000 |
|
3. Galian tanah lunak |
M3 |
5.500 |
|
II. PENGURUGAN/PEMATANGAN TANAH DENGAN TENAGA MANUSIA (TIDAK TERMASUK BAHAN) |
||
|
1. Jarak angkut < 29 m |
M3 |
7.750 |
|
2. Jarak angkut 30 - 39 m |
M3 |
9.350 |
|
3. Jarak angkut 40 - 49 m |
M3 |
9.650 |
|
4. Jarak angkut 50 - 99 m |
M3 |
9.900 |
|
5. Jarak angkut 100 - 200 m |
M3 |
14.000 |
|
III. PENGURUGAN/PEMATANGAN TANAH DENGAN ALAT BERAT (TERMASUK BAHAN) |
||
|
1. Jarak angkut 5 Km |
M3 |
16.500 |
|
2. Jarak angkut 10 Km |
M3 |
25.200 |
|
3. Jarak angkut 15 Km |
M3 |
30.000 |
|
4. Perataan/penggusuran tanah |
||
|
a. Jarak gusur s.d. 14 m |
M3 |
1.350 |
|
b. Jarak gusur s.d. 30 m |
M3 |
1.900 |
|
IV. PEKERJAAN CERUCUK |
||
|
1. Bambu : |
||
|
- panjang 2 m |
Batang |
1.550 |
|
- panjang 3 m |
Batang |
2.200 |
|
2. Dolken : |
||
|
- panjang 2 m |
Batang |
2.750 |
|
- panjang 3 m |
Batang |
4.250 |
|
V. GEBALAN / LEMPENGAN RUMPUT |
||
|
1. Jarak angkut <= 30 m |
M2 |
1.020 |
|
2. Jarak angkut 30 - 50 m |
M2 |
1.375 |
|
3. Jarak angkut 50 - 100 m |
M2 |
1.300 |
|
4. Jarak angkut 100 - 200 m |
M2 |
1.800 |
Membuat Komentar